III. RESTORATION PROCESS

III.2. PLANNING

1. Main stages provided for the control/reduction of degradation causes (passive restoration)?
Please specify when and for how long were these stages to be carried out:
 

2. Main stages provided for the field work (active restoration)?.
Please specify when and for how long were these stages to be carried out?: 
1970: Plantation of Pinus pinea and eucalyptus; 1981-85: Grazing (250 sheep); Clearing; 1986-90: Pastoral improvement: over-seeding (450 sheep); 1991-95: Promotion of cork oak regeneration (650 sheep); 1996-99: Plantations 

3. Is the project related to any previous or parallel project? 
Yes
Description: Fire protection projects  

4. Has a previous/parallel project been described in a different form?
Yes
Project(s) code(s):
Esterel 

5. Does the forest have a management plan?
Yes
What is the legal/policy framework?:
 

III.3. COST, FINANCING, AND PARTICIPANTS

1. Project cost & financing 
a) Total cost of implementation (Euros): 1 106 110 
Ref. Date: 2002 
b) Average annual cost for maintenance (Euros): 20 140 
Ref. Date: 2002 
c) Sources of financing: EEC, State, Region, Department, Commune, ONF, sheep farmer  
d) Other relevant information:  

2. International, national or regional programmes and/or plans related to the project: 
 

3. Agencies/groups involved in the project:
Role Private company Public company Publc administ. Local association NGOs Other Name
Landowner  - - YES - - - State, communes 
Desing & Planning  - - YES - - - INRA, ONF 
Implementation (fieldwork)  YES - YES - - - Maille, ONF 
Management (tech. Direction)  - - YES - - - ONF 
Econimical explotation  YES - - - - -  
Monitoring  - - YES - - - INRA 